Recently, Power Construction Corporation of China Guizhou Engineering Co., Ltd. successfully won the bid to sign the Inner Mongolia Xianhuang Banner Shengshi Xinyuan Wind Power Co., Ltd 125 MW wind power project contract.

中国电力建设.jpg

It is reported that the wind power project design and installation of 37 sets of single-capacity 2.0 MW wind turbines and 17 sets of single-capacity 3.0 MW wind turbines, with a total installed capacity of 125 MW. The construction period is 365 days, expected to start on April 18, 2018 and be completed on April 17, 2019.

After the completion of the wind power project, it is of great significance to promote the adjustment of local energy structure, environmental protection and economic sustainable development.